3 BHK residential property · Raw / pre-finishing stage. An illustrative report that shows our format — not an inspection of any real property.
| Report status | Sample / demonstration |
|---|---|
| Report no. | VB-SAMPLE-001 |
| Inspection type | Construction quality & defect inspection |
| Inspection stage | Raw / pre-finishing |
| Prepared by | VeriBuild Technical Inspection Team |
The observations and photographs are illustrative and are not an inspection of the client’s property.
This sample demonstrates how VeriBuild documents a residential inspection at the raw / pre-finishing stage. The objective is to identify visible workmanship concerns, incomplete work and items requiring verification before they are concealed by finishing.
| Inspection area | Illustrative outcome | Priority |
|---|---|---|
| Civil & masonry | Wall/plaster levels and RCC–masonry junctions require review. | MODERATE / MAJOR |
| Waterproofing | Confirm completion and test readiness before tiling. | CRITICAL |
| Plumbing | Verify points, slopes and leakage testing. | MAJOR |
| Electrical | Check locations and concealed provisions against drawings. | MAJOR |
| Flooring | Verify levels and slopes before final finishes. | MAJOR |
Civil and masonry workmanship; plaster and surface condition; visible RCC–masonry junctions; floor levels and wet-area slopes; waterproofing test-readiness; visible plumbing and electrical provisions; openings; kitchen, toilet, utility and balcony provisions; and general workmanship/snags.
Method: visual inspection, accessible dimensional/level checks, review against drawings/specifications where provided, and photographic documentation. Specialised or destructive testing is separately agreed where required.
| CRITICAL | Immediate attention / testing before proceeding |
|---|---|
| MAJOR | Rectify or verify before covering/finishing |
| MODERATE | Correct during current stage |
| MINOR | Finishing / workmanship improvement |
| ACCEPTABLE | No visible concern within inspection scope |
Location: Living Room — East Wall
Observation: Visible surface variation in a portion of plaster.
Potential impact: May affect final paint finish and increase putty consumption.
Recommended action: Check wall level/plumb and rectify before putty and painting.
Location: Bedroom 1 — Door-side wall
Observation: Junction treatment should be checked before final finishing.
Potential impact: Untreated movement may contribute to recurring surface cracks.
Recommended action: Verify approved junction treatment; provide suitable crack-control treatment where specified.

Location: Master Toilet
Observation: Completion and test-readiness should be confirmed before tiling.
Potential impact: Concealed leakage may damage finishes after installation.
Recommended action: Complete as specified and conduct applicable pond/leakage test before covering.
Location: Balcony
Observation: Drainage slope toward designated outlet should be verified.
Potential impact: Insufficient slope may cause water stagnation or seepage risk.
Recommended action: Check with suitable instrument and rectify before final floor finish.
Location: Kitchen
Recommended verification: Check water supply, waste and appliance points against approved layout; verify coordinates, levels, slopes and access before closing walls/floors.
Location: Common Toilet
Recommended verification: Verify drain points and floor slope; conduct water-flow testing before tiling.
Location: Bedroom 2
Recommended verification: Cross-check switch/socket and appliance provisions, conduit continuity and circuit allocation against approved layout.
Location: Electrical DB Area
Recommended verification: Verify DB arrangement, circuit identification and earthing provisions against design through the responsible electrical professional.
Photographs are supplied as illustrative construction-site examples. Captions describe visible context only; they do not establish compliance or a confirmed defect.






Client action: the actual report includes a numbered snag register, photographs, location references, priority and recommended corrective action. Re-inspection can be arranged after rectification.
Independent construction quality · Defect inspection · Snagging
Interior inspection · Technical due diligence
veribuild.in · info@veribuild.in
Sample only: this report demonstrates VeriBuild’s report format and is not a statement about any specific property. Actual findings are based only on the scheduled inspection and information made available to the inspection team.